Procedures - Project Hand-Over Procedure

Project Hand-Over Procedure

01 Upon the completion of both major work (precast installation, grouting & related in-situ works) and minor work (repair & finishing work) of the project, Site Engineer shall arrange an appointment with Client’s site representative for hand over inspection.

02 Site Engineer shall prepare the Hand-Over Checklist which is to be filled by Client’s site representative for every location of the project inspected.

03 Site Engineer shall prepare the Defect Checklist which is to be filled by Client’s site representative for every defective item spotted. Each defective item must be photographed and attached together with the Defect Checklist.

04 Site Engineer shall arrange to start remedial work immediately according to the defective item recorded in the Defect Checklist.

05 Once the remedial work complete, arrange another appointment with Client’s site representative for another round of hand-over inspection to verify the remedial work.

06 Client’s site representative shall sign off the Hand-Over Checklist upon the completion of hand-over inspection.

07 The Project Hand-Over Procedure complete.