Procedures - Precast Component Receiving Procedure

Precast Component Receiving Procedure

01 Upon the arrival of the precast component, the quality of precast components delivered shall be checked and the type & quantity of precast component (as indicate on the Delivery Order-DO) shall be verified by the Site Engineer/Supervisor prior to offloading.

02 Any major/minor defects on the precast component need to be recorded on the DO with the acknowledgement of the trailer’s driver.

03 If the type & quantity of the precast component delivered are not tally with DO, the discrepancy need to be recorded in the DO with the acknowledgement of the trailer’s driver.

04 Photos shall be taken on the major/minor defects on the precast component while the precast component still on the trailer, if possible.

05 Site Engineer/Supervisor shall record the arrival/departure date & time of trailer on the DO.

06 Site Engineer/Supervisor shall check with Precast Supplier every morning regarding the delivery of that day.

07 Precast component receiving procedure complete.