Procedures - Precast Component Ordering Procedure

Precast Component Ordering Procedure

01Site Engineer shall update the precast installation progress and forecast the precast installation to identify the precast component required from Precast Supplier.

02Site Engineer shall keep track on type & quantity of precast component stored at site. Compare the list of precast component required and precast component stored at site to avoid ‘double’ order on certain precast component.

03Any changes on the delivery arrangement must be informed to Precast Supplier by issue another new Precast Element Order Form.

04Site Engineer shall list down the precast component required in the Precast Element Order Form and send to Precast Supplier via fax or e-mail by 12pm. Site Engineer shall allow 2 days of delivery lead time to Precast Supplier for delivery arrangement.

05Precast component ordering procedure complete.